From: Kristian E. Nysome
<KNysome@waukesha-wi.gov>
Date: Fri, Jun 18, 2021 at 1:51 PM
Subject: Area 1 & 2 Flood Mitigation (Rolling Ridge Ditch Grading) Project
Update
To:Windings Residents
Good
Afternoon,
The Rolling Ridge Ditch Grading project is anticipated to start mid-to-late next week, June 21-25 (weather dependent).
The grading project will consist of the following work:
- Clearing and Grubbing
- Grading
- Seeding and restoration
Future Work (week of June 21):
- Clearing and grubbing is anticipated to start mid-to-late next week (see attached project limits map for the grading limits).
Traffic Restrictions:
- None - traffic and access to driveways will be maintained throughout the project. Traffic control will be placed along the shoulder of Rolling Ridge Dr, as needed.
Please feel free to call or email with any questions or concerns.
Thanks,
Kristian Nysome
Project Engineer
City of Waukesha – Engineering Division
201 Delafield St. Waukesha, WI 53188
O: (262) 524-3578 M: (262) 225-8327